Speedy is based on the B.R. (W) Class 1500 Locomotive, when I purchased the engine it had been in use for quite a long time and was starting to show signs of wear. I decided to carry out the work out in two stages, but then problems with a leak on the boiler added a third stage. Stage One:- Correct some problems with the water tanks, re-pipe various supplies, move some of the controls and add more detailing. Stage two:- Renew the smokebox pipework including a new blast pipe and adding an improved radiant supaheater unit. Stage three:- Making a new boiler, which will included a new steam valve to get the steam brake working plus adding a hand brake into the linkage. |
![]() |
| This is the engine as purchased in the year 2000. |
![]() |
| Tank showing remedial work underway to correct a problem with its shape. |
![]() |
| The left side water tank being re-painted. |
![]() |
| Out on the track for the first time after completing stage one |
| Stage Two of the Restoration |
![]() |
| The old smokebox and blast pipe before re-making. |
![]() |
| New and old supaheater tube assembly. |
![]() |
| New supaheater tubes and blast pipe being installed. |
![]() |
| Smokebox being cleaning and refurbished. |
![]() |
| Smokebox refitted and detailing being added. |
![]() |
| Detailing and painting nearly finished, she looks as good as new. |
![]() |
| Another detail picture. |
![]() |
| I am running "Speedy" on the club's raised
track. Picture taken in December 2003 at our 'Christmas Steam Up' day. |
![]() |
| Another picture taken at the 2003 Christmas steam up. |
| Stage Three of the Restoration |
| 2005 - Due to problems with a persistent leak in
the boiler that could not be cured without major surgery, I decided to make a new boiler (with help from several club members). |
![]() |
| Outer firebox and barrel with inner firebox
wrapper. Note the superheater holes have yet to be drilled out and the wooden formers in the background used for shaping the wrappers. |
![]() |
| Checking the fit of the boiler to the loco. Note the use of large jubilee clips to hold the barrel together. |
| I am building a range of wagons from kits, but intend adding additional detailing. |
![]() |
| I purchased the driving trolley and then made the
various storage and coal carrying boxes to fit. |
![]() |
| I am adding more wagons to my 'Train'. |
| This picture taken in July 2006, (with its new Boiler) |